AT A GLANCE

Asset Type

Nuclear Power – Turbine Condenser

Project Scope

Field Machining & Expansion Bellows Removal/Replacement

Environment

Confined Space, Elevated Temperature, Active Welding Nearby

Bellows Sizes

12", 16", 24", 36"

Quantity

8 bellows in each of 3 condensers

Special Requirements

Minimal Foreign Material Entry (FME), low-profile cutting equipment, strict clearance limitations

Schedule Impact

Contributed to outage reduction from 32 to 28 days

The Challenge

Nextra Energy approached Hydratight with a critical machining task during a time-sensitive Unit 1 outage at Point Beach Nuclear. Three condensers required removal of eight expansion bellows each - components essential for managing thermal expansion under the turbine. The bellows were positioned vertically at the very top of the condenser, extremely close to the turbine casing and to each other. Clearances were tight: some cuts were within 3 inches of the turbine and 6 inches apart. Complication added to complexity

Confined space environment

with limited access for equipment and personnel

Requirement for minimal FME

(Foreign Material Entry) - due to vertical orientation above the condenser

Simultaneous welding operations

creating heat exposure and air-quality concerns

Need for lightweight equipment

capable of precision cuts without extensive rigging

The Hydratight Solution

Hydratight’s engineering team conducted a full review of condenser prints, bellows design, and access constraints. The solution combined:

1. Purpose-built, low-profile machining equipment

We deployed a range of Mirage DL Ricci NB clamshell cutters, selected specifically for their lightweight design, rigidity, and extremely low profile. This allowed crews to manoeuvre safely in the confined turbine deck area without sacrificing cutting accuracy.

2. Custom tooling for zero-compromise FME control

Because all cuts were vertical, Hydratight designed specialised tooling that prevented foreign material entry while still enabling smooth cutting and beveling operations.

3. Field machining trailer pre-stocked for continuity

To protect the outage timeline, we mobilised:

- Fully equipped machining trailer

- Spare equipment and cutting tools

- Additional personnel trained for confined-space machining

This ensured no unplanned delays from equipment swaps or tool shortages.

4. Coordinated multi-discipline safety management

Hydratight worked closely with Nextra Energy craft labor to manage:

- Heat stress risk

- Ventilation and air monitoring

- Limited personnel density in the condenser

Safety and productivity were maintained throughout the project.

The Results

Hydratight’s precision planning and onsite execution directly contributed to Nextra Energy successfully reducing the overall outage schedule from 32 days to 28 days - a significant achievement for a nuclear facility. Key outcomes included:

Zero FME incidents

despite vertical machining and tight clearances

Safe and efficient rigging

enabled by lightweight clamshell systems

No machining delays

supported by onsite spare equipment

Accurate, right-first-time cutting and beveling

ensuring reliable installation of new bellows

Strong client confidence

reinforced by delivering within challenging spatial and thermal constraints

Ready to improve reliability and reduce outage time?

Hydratight provides specialised field machining solutions engineered for the most constrained, sensitive, and high-risk environments.
If you need precision, safety, and zero compromise on schedule, we’re ready to help.
Contact Hydratight to discuss your project.

Terms & conditions | Privacy policy | © 2026 Hydratight. All rights reserved.

Terms & conditions | Privacy policy
© 2026 Hydratight. All rights reserved.

REACH US